MetaKON
Provides
Siemens Transportation Systems
Nowadays
many companies consider the Engineering and Product Data Management of being the
key technology for optimizing the product development and project processing.
From the using of leading-edge EDM/PDM-System one expects reduced costs and
times for processing development and improved involvement of supplier and
customer as well as a reliable document and data management. These and other
aims are also pursued by Siemens, Transportation Systems, in Braunschweig, who
has productively been working with MetaKON, the EDM/PDM-solution based on
Metaphase, of the company ECS GmbH in Neumarkt since the mid of September of
this year.
At
present, MetaKON is applied by Siemens Transportation Systems in its
business unit TS 1, the operational management systems for long-distance
transport. TS 1 develops and produces plants and systems for the long-distance
rail transport and offers protection and control systems as for example train
control systems. The product range of the business unit
also covers components like power switch machines and signals, electronic
train controlling devices as well as complex electronic signaling devices.
Among
other things, presently Siemens TS equips the new ICE 3* with an electronic
control status, first train of which are leaving the factories. This provides
the ICE-train leader for example with information about distances, it monitors
the speed or stops the train on time and automatically, if it is operationally
required.
In
the beginning of the 90‘s, Siemens TS 1 in Braunschweig has already planned to
introduce the ERP/PPS-Software „SAP R/3“ in parallel, in order to support
sales, purchasing, production planning,
project controlling and accounting
as well as to introduce EDM/PDM-systems of Metaphase for supporting the
Engineering Process. After careful consideration, these plans, however, were
turned down again, since in the expert’s opinion the introduction of two
parallel systems at the same time could largely influence work processes as well
as organization, thus leading to high expenditures and causing lot of problems.
SAP R/3 was introduced
before EDM-System
That’s
why the introduction of SAP/3 was initially tackled. The R/3 has productively
been used at Siemens TS 1, since the end of 1996. At that time also the theme
EDM/PDM was taken up and an according EDM/PDM-Project was initiated. The primary
aims were clearly put into words: An EDM/PDM-System should support the process
of technical business activities, should help to considerably improve the
Configuration-Management and finally ensure the document and data consistancy. A
reduction in costs of at least 15% was planned in the section of Engineering as
a monetary aim.
Jens
Haller, appointed as head of the EDM-project in the beginning of 1997, explained
the initial situation: „From the beginning the EDM-project had a very big
strategic importance“. It had a very positive effect that the aims were
clearly defined and that the project-team got a strong backing
from the management. Not only meetings within the project-team were held,
but also greater in-house-information events
and discussion groups of users were held. „From the start, thus, the project
and the team meet with a great acceptance of the users“, underlines Jens
Haller. Alone tree members of the team could exclusively look after the
preparation, system choice and working hours. Moreover, representatives of the
affected departments and later the user were integrated into the team, so that,
as a result of intensive meetings and extensive analysis the demand were
determined carefully and a step-by-step plan for the introduction of the system
was worked out. The latter included to find at first a solution for the
document-management and afterwards, to start with the themes Workflow- and
Product-Data-Management.
In
the selection of the system, the project team acted systematically. Initially,
publications of the professional journals as well as frequentations of fairs and
companies of system suppliers were analyzed. Then the number of systems, which
should be examined more exactly, were limited to four systems. Afterwards, a
detailed analysis of the products followed, at which not only the functionality
buts also strategic points of view were of immediate importance.
Examples
for this were the position of the
supplier on the market situation, extent of the developing team, a certain
security that the respective company will still exist after five to 10 years as
well as the list of the reference customers.
At
first sight, all criterions seemed to be fulfilled by Metaphase. The system has
a high market share, the producer Metaphase Technology is acting world-wide –
for us also an important factor, as we do business on international markets with
local presence and with local value-added. The enterprise Metaphase Technologies
offer security for the future as a 100%-subsidiary of SDRC. Moreover, the
developing team consists of about 300 developers. This is by the way of
comparison a very high number if you look at other suppliers.
However,
the final ideal solution was still not found with Metaphase. „Metaphase is a
system, which offers a large functionality and is very flexible for adapting“,
continues Haller. „It is a kind of construction kit, by which every demanded
solution for applying can be practically built up specific to the company. As a
rule, however, his requires quite high efforts in adapting and programming,
which we wanted to avoid as far as possible.“
These
were the reasons why the employees at Siemens had a good nose for the Turnkey
Application of MetaKON of ECS and came to the conclusion that this would be the
best solution. „Among other things we especially liked very much the new DoMS-Module
of MetaKON, which comes up with graphical file structures“, says Haller.
„They ease the change over to the system, the finding of documents and the
respectively systematical structuring of projects and documents, as we need
them. (Fig. 1)
For
MetaKON the deciding factors were, moreover, the variety of available linkage or
possibilities of integration with CAD and ERP/PPS-Systems. Thus, for the EDM/PDM-System
are among other things, interface for R/3 as well as for I-DEAS, Pro/Engineer,
CATIA, AutoCAD, Medusa, ME10, Solid Designer, Solid Edge, ObjectD and
Unigraphics available. Moreover, a specific module named „Global Interface“
(GIF) will be offered, by which the most varying systems can be tied up.
The
interfaces are very important to us, as our system environment is very heterogeneous“, says Haller. „We have besides Office –Applications a huge
number of different Mechanical-EDA- and Electronic-CAD-Solutions like AutoCAD,
Mentor, ELCAD and also self-developed special software, for example for the
projecting of signaling devices. These systems have to be integrated as best as
possible. MetaKON, offers a large number of connections to
Mechanical-CAD-Systems on the basis of the „Global Interface“-Interface. At
present, the interfaces to CAD-Systems for electrical engineering and
electronics at ECS are also realized on the basis of GIF-Tools.
The
experts were aware of the fact that also the introduction of a turnkey EDM/PDM-System
will take up quite several months. The provision of hardware and software,
installation and configuration, the scanning of documents, the deposit into the
EDM/PDM-database as well as the linking of already existing software are also
taking long time if hardly a customizing must be realized.
Nevertheless,
only less than six months passed from the decision of purchasing in April 1998
up to the completion of the first project phase and this system has been
productively applied since the mid-September of this year.
„As
system supplier and system integrator, Siemens Nixdorf Business Services (SBS)
became a partner of ours. From our point of view, this project size is the most
effective way“ says Haller.
Nearly
500 users, nevertheless, apply the Siemens‘ EDM/PDM-system. Further 500 users
are firmly expected. The decisive factor favoring SBS has also consist in the
readiness to accept the short period of six months. „Moreover, the company
could offer us the takeover of the main contractor for the software and
hardware, so that only and solely SBS is responsible for the elimination of
problems and errors“, adds Haller.
Linking
to SAP R/3 within the scope of the second project phase
By
using the SBS-method „Chestra“ in system conception and adaptation, the team
made extremely rapid progresses. Whereas usually in the first instance all
requirements are detailed put together in set books and the system is
consequently configured based on it, the definition of requirement and the
configuration or adaptation of the software is interactively refined by using „Chestra“.
Other system integrators and consulting companies e.g. CDS Ploenzke also decide
to make user similar procedure.
As
the productivity switch coming out in September, documents, as well as software
could now be administrated e.g. for monitoring equipments using the EDM/PDM
system. AutoCAD was integrated so far, among the applied CAD-systems,
additionally the office-applications. During second project phase, the EDA-system
is expected to be integrated by Mentor and the Electrical
Engineering-CAD-package ELCAD by Aucotec.
Furthermore,
by means of the second project phase it is intended that the product data be
managed via MetaKON. This is to say enabling to exactly understand all
modifications and components for every project. In this connection, the system
shows that the modification’s history is completed: Within the scope of this
phase it is supposed to integrate SAP R/3, too, so that material stems, parts‘
lists and modifications can be automatically transmitted to the ERP/PPS-system.
„Metaphase/MetaKON
renders extremely efficient workings for part’s administration and parts‘
lists“, realizes Haller. Any parts‘ lists approaches e.g. could be defined.
Connectors can be built-up between the separate approaches as for example
construction, manufacturing and marketing parts‘ list. By this way it can be
determined, which components of the parts list e.g. appears
in the manufacturing part’s list are transmitted to other approaches. In case
of orders, the respective parts‘ lists will be electronically transmitted to
the SAP-system.
The
third project phase makes use of the workflow-functionality in such a way that
the business processes of individual part sections of VT 1 can be developed in
an automatic and pictured manner. For this purpose, for the time being, the
respective business processes are analyzed and documented, and the
implementation in the EDM/PDM-software is prepared.
For
having access to the EDM/PDM-database, Windows-NT and Unix-clients are applied
dependent on the respective workstation. The server-hardware-platform for
MetaKON is forming two Unix-Server of the type „Enterprise 3500“ of Sun
Microsystems, of which the most important components are redundantly laid-out.
Should a machine fail, the second server is changing in few minutes from
Stand-by-mode to the operation mode, and the user is again on the EDM/PDM-system.
Besides, the servers are equipped with a RAID-system, which allows to add or
exchange fixed discs e.g. during the operation of the server.
Consideration
of economic efficiency projects high savings
In
many respects Siemens VT’s staff promises themselves advantages through the
EDM/PDM-solution. On the one hand, the system helps to ensure the consistency of
data and documents, on the other hand it helps to reduce the additional time
caused in advance by missing or not finding information and documents. Moreover,
the illustration of the modification-management in the system will present
important advantages and will enable a strong rationalization of the
engineering-processes. „We estimate that we will save about 15 to 20% of the
costs in the affected fields. During an average project, within its scope
roughly 15.000 documents must be provided and administered. Thus according to our
calculations savings at the rate of approximately 800.000 marks should be
achieved every year.
In
the long-term it is planned to make the EDM/PDM-system useful also for the
different national places of business, for the partners co-operating with TS as
well as for customer and suppliers. Consequently, the number of the users
reaching at the same time the software and data, can require a further
expansion of the hardware. As the Unix-Server-system as well as the EDM/PDM-software
are scaleable and for this case we are extremely prepared.
Concerning
this matter, finally Jens Haller means: “By MetaKON we use an EDM/PDM-system
allowing also the divided data management. Above all, this is very important for
the system order with companies situated abroad”.
Figures
 |
Fig.
1: Using DMS-module of MetaKON, documents and datas can be
organized very clearly in a graphical file structure.(Fig.:
Siemens AG, Braunschweig)
|
 |
Fig.
2: Graphics of product structures are shown in the EDM-system. The
user thereby obtains also the review of complex structures.
(Fig.: Siemens AG, Braunschweig)
|
 |
Fig.
3: In future, the different national places of businesses (NPB),
product and system companies as well as customer and suppliers
should reach at an EDM-data bases by a data protection security
(Firewall).
(Fig.: Siemens AG, Braunschweig)
|
 |
Fig.
4: The products of Siemens Transportation Systems as well as management systems
regulate the rail traffic in many countries all over the world.
|
 |
Fig.
5: Siemens TS 1 constructs and produces projects and systems for
the long-distance traffics on rail e.g. train influencing systems
and electronical multiple-unit control.
|